Metrolinx

Elevating standards and minimising incidents

TXM Consult is embedded into the Rapid Transit Programme team supportingt the delivery of the Eglinton Crosstown, Finch West and Hazel McCallion LRT.

5 Functional Areas Supported
2 Level 3 VIS Centers
9 Workstreams developed for RSD

The Challenges

  • Land Acquisition and Property Disputes: Acquiring the necessary land, particularly in densely populated urban areas, can be time-consuming and costly. Additionally, there can be resistance from property owners or communities affected by new routes, leading to legal disputes or delays.
  • Construction and Traffic Disruptions: Managing construction while minimising impacts on daily commuters, businesses, and local residents is a complex task. Delays in construction schedules, due to factors like weather, unforeseen underground conditions, or issues with contractors, can further complicate project timelines.

The Solutions

  • Project Governance: Established a structured Visualisation Framework to engage the team in highlighting concerns and committing to actions and timelines.
  • Expertise Across Workstreams: Deployed specialists in key areas such as Systems Assurance, Systems Integration, Planning, Rolling Stock, and Operations
  • Stakeholder Management: Worked with the various Owners, Constructors, Maintainers and Operators to ensure collaboration and consistent communication.

The results:

  • 50% Fewer Meetings
  • 4 Key Stakeholders Aligned
  • 9 Workstreams Defined